
Monitoring a Construction Site to Provide Rail Access to the Depot
project start
Services
Construction Site Monitoring
Sensors



Monitoring a Construction Site to Provide Rail Access to the Depot
PROJECT OVERVIEW
As part of the Transport for Wales rail system, a rolling stock depot, built at Taffs Well, required a bridge to connect it to the rail station. Before building the new bridge a sheet pile wall had to be installed in order to retain earth and other filling material during piling activities.

MONITORING OBJECTIVE
The monitoring system provided by Move Solutions through one of their UK supplier, Korec Group, collects real-time data of the sheet pile wall, 24 hours a day, 7 days a week. The aim is to identify any changes in the behaviour and position of the wall so as to avoid structural failure after its removal.
MONITORING SYSTEM
The system installed consisted of the following elements:
- 16 Triaxial Tiltmeters
- Mounted on 1-meter magnetic tilt beams
- Mounted on magnet mounts
- 1 Gateway
- Supported by a Backup Power System
The Tiltmeters and SHM Accelerometers were installed along the length of the sheet pile wall to provide comparable data on its position and frequency response of the wall during and after piling works. The sensors were installed using magnet mounts so that they could be easily transferred to different sheet piles afterwards. The SHM Accelerometers provided both thresholds triggered vibration readings and scheduled synchronized readings for remote modal shape analysis via the Move Cloud Platform.
The monitoring system installation was completed in 6 hours: that included the assembly of the Tiltmeters, the Tilt-beams and the SHM Accelerometers to the magnet mounts, which this time was completed on-site due to the short-notice before the installation. All sensors were online and communicating with the Gateway within 20 minutes from its activation.
A backup power system was required for continuous monitoring as the primary one on site was switched off overnight and during the weekends.
The monitoring installation will be in situ for approximately 12 months in total with the sensors being eventually repositioned onto a new sheet pile retaining wall.

PROJECT NOTES
Transport for Wales manages the whole rail infrastructure in Wales.
The monitoring system sensors were supplied by Korec Group, an official Move Solutions reseller for the UK market.
Dyna-mo Instruments provided the magnetic mount kits, tilt beams and the backup power system. The monitoring devices are powered by a generator during the day, while the backup power system takes over overnight and at weekends. When the generator is switched back on the backup power system recharges from the generator power.
Amey designed the monitoring system, installation location and alarm activation.
Alun Griffiths are the contractor onsite completing the build of the new wall and the removal of the old. They were also responsible for carrying out the system installation.
CONCLUSION
The structural health monitoring system has provided valuable data and visualization via the Move Cloud Platform of the behaviour of the wall since the start of the piling activities. Significant vibration readings have been able to be directly correlated to the proximity of each sensor to the piling works. It is anticipated that the wall will present a change in its behaviour, which will be observed via the SHM Accelerometers when the wall anchors are cut on the existing retaining wall in Q2 2022.
Other case studies
Bridge Monitoring
Wireless Monitoring of the Zambeccari Bridge in Tuscany
The Zambeccari bridge in Pontremoli was built in the early 1900s on the Verde stream. It is a reinforced concrete bridge developed on two spans of the same length. In May 2020, the closure to both vehicular and pedestrian traffic is ordered for structural checks. The objective of the temporary closure of the structure is to clarify the state of health of the bridge and its structural degradation. After verifying the state of the Zambeccari bridge by the Vega Engineering Company, the structure was reopened with a reduced carriageway. Vega has prepared, with the approval of the municipality, the insertion of a continuous and remote structural monitoring system.
Pontremoli, Tuscany, Italy
Bridge Monitoring
Dynamic Monitoring of the Vespucci Bridge in Florence
The Vespucci bridge is one of the central bridges of Florence that allows you to join the San Frediano district to the rest of the city, separated by the Arno river. It is a structure in c.a.p. arch divided into 3 spans, with an overall length of 162m. Designed by Riccardo Morandi and built between 1954-1957, suffers from deterioration of the concrete, like many works of the time. This deterioration has affected the two piers even more markedly, especially the one on the left (San Frediano side) due to the erosion of the riverbed by the currents of the Arno river. This structural deterioration required continuous monitoring and safety works.
Florence, Italy
Bridge Monitoring
Tilt and Vibration Monitoring of a Railway Bridge
The bridge located on the Scrivia river, one of the arteries of the homonymous valley, is a structure all about 160 meters long and is divided into 7 spans with lowered arches, in reinforced concrete. Built-in the early 1900s, it served as a road and rail bridge for years. In 1980 the extension of the bridge over the Scrivia (structure in reinforced concrete with slab and beams) was carried out and also a shift of the railway network to its own site, thus splitting the two uses. To monitor the health of the bridge, a wireless sensor network was installed consisting of DECK to monitor displacement and Triaxial Tiltmeter to monitor the inclination of the […]
Casella, Genoa, Italy
Historic Buildings Monitoring
Monitoring a Historic Windmill Undergoing Repair Works
At the beginning of 2022, the SPAB and their Mills Section started a repair project at Kibworth Harcourt Mill, an outstanding historic post mill at Kibworth Harcourt in Leicestershire. Most of its structure dates back to 1711 or earlier and its interior is covered with graffiti of millers who worked there in the past. It is a Grade II listed building and a Scheduled Ancient Monument. Kibworth Mill is the last survivor out of the 211 post mills in Leicestershire, which makes it an important part of local and national milling heritage.
Leicestershire, UK