Dynamic and Static Load Tests of a Metal Bridge on a Construction Site
project start
Services
Construction Site Monitoring
Sensors



Dynamic and Static Load Tests of a Metal Bridge on a Construction Site
PROJECT OVERVIEW
A temporary metal bridge was built to join the two banks of the river that divides the construction site of the new bridge in San Lorenzo di Sebato, in Trentino Alto Adige. The main function of this temporary structure, on a construction site, is to allow the passage of vehicles and heavy vehicles necessary during the development of the construction site.
The purpose of this construction site is to build the new bridge that will connect the Pusteria state road with the new access to Val Badia. The structure of this new bridge is 144 meters long and 1,040 tons heavy.
The temporary metal bridge, of fundamental importance for the construction site, was installed at the end of June 2019 and will only remain operational for a few years. In the first period of the construction site’s development, Move Solutions was commissioned to monitor this temporary structure and to carry out load tests both in static and dynamic conditions.
Triaxial Tiltmeters were used to perform the static deformation tests. The metal bridge was loaded in the centre with some trucks, waiting for the lowering of the structure. Subsequently, the deformation data were displayed and analyzed using the automatic tool on the Move Cloud Platform. Subsequently, two DECK sensors were mounted for the detection of dynamic displacement, installed in the centre of the bridge, one on each side. Dynamic oscillation tests were then carried out when the trucks passed.
These dynamic and static load tests were fundamental to understand the structural reliability of the bridge, to ensure its effective operation. Structures of this type are forced to undergo dynamic stresses and very important continuous loads given the intensive use for which they were designed.
For the installation of the beams, which are 80 meters long, a crane 90 meters high and weighing 300 tons had to be positioned, capable of lifting to 600 tons of weight.
The works for the construction of the new road entrance to Val Badia with the tunnel are carried out by a business association led by Strabag. The completion of the interventions is scheduled for Christmas 2021. The new access to Val Badia includes the Floronzo tunnel, 400 meters long, continues with the 144-meter bridge over the Kniepass artificial lake which leads to a roundabout that will serve as a connection with the Val Pusteria state road (SS 49).



Other case studies
Bridge Monitoring
Wireless Monitoring of the Zambeccari Bridge in Tuscany
The Zambeccari bridge in Pontremoli was built in the early 1900s on the Verde stream. It is a reinforced concrete bridge developed on two spans of the same length. In May 2020, the closure to both vehicular and pedestrian traffic is ordered for structural checks. The objective of the temporary closure of the structure is to clarify the state of health of the bridge and its structural degradation. After verifying the state of the Zambeccari bridge by the Vega Engineering Company, the structure was reopened with a reduced carriageway. Vega has prepared, with the approval of the municipality, the insertion of a continuous and remote structural monitoring system.
Pontremoli, Tuscany, Italy
Bridge Monitoring
Dynamic Monitoring of the Vespucci Bridge in Florence
The Vespucci bridge is one of the central bridges of Florence that allows you to join the San Frediano district to the rest of the city, separated by the Arno river. It is a structure in c.a.p. arch divided into 3 spans, with an overall length of 162m. Designed by Riccardo Morandi and built between 1954-1957, suffers from deterioration of the concrete, like many works of the time. This deterioration has affected the two piers even more markedly, especially the one on the left (San Frediano side) due to the erosion of the riverbed by the currents of the Arno river. This structural deterioration required continuous monitoring and safety works.
Florence, Italy
Bridge Monitoring
Tilt and Vibration Monitoring of a Railway Bridge
The bridge located on the Scrivia river, one of the arteries of the homonymous valley, is a structure all about 160 meters long and is divided into 7 spans with lowered arches, in reinforced concrete. Built-in the early 1900s, it served as a road and rail bridge for years. In 1980 the extension of the bridge over the Scrivia (structure in reinforced concrete with slab and beams) was carried out and also a shift of the railway network to its own site, thus splitting the two uses. To monitor the health of the bridge, a wireless sensor network was installed consisting of DECK to monitor displacement and Triaxial Tiltmeter to monitor the inclination of the […]
Casella, Genoa, Italy
Historic Buildings Monitoring
Monitoring a Historic Windmill Undergoing Repair Works
At the beginning of 2022, the SPAB and their Mills Section started a repair project at Kibworth Harcourt Mill, an outstanding historic post mill at Kibworth Harcourt in Leicestershire. Most of its structure dates back to 1711 or earlier and its interior is covered with graffiti of millers who worked there in the past. It is a Grade II listed building and a Scheduled Ancient Monument. Kibworth Mill is the last survivor out of the 211 post mills in Leicestershire, which makes it an important part of local and national milling heritage.
Leicestershire, UK