Dynamic and Static Load Tests of a Metal Bridge on a Construction Site

Overview

A temporary metal bridge was built to join the two banks of the river that divides the construction site of the new bridge in San Lorenzo di Sebato, in Trentino Alto Adige. The main function of this temporary structure, on a construction site, is to allow the passage of vehicles and heavy vehicles necessary during the development of the construction site.
The purpose of this construction site is to build the new bridge that will connect the Pusteria state road with the new access to Val Badia. The structure of this new bridge is 144 meters long and 1,040 tons heavy.

The temporary metal bridge, of fundamental importance for the construction site, was installed at the end of June 2019 and will only remain operational for a few years. In the first period of the construction site’s development, Move Solutions was commissioned to monitor this temporary structure and to carry out load tests both in static and dynamic conditions.
Triaxial Tiltmeters were used to perform the static deformation tests. The metal bridge was loaded in the centre with some trucks, waiting for the lowering of the structure. Subsequently, the deformation data were displayed and analyzed using the automatic tool on the Move Cloud Platform. Subsequently, two DECK sensors were mounted for the detection of dynamic displacement, installed in the centre of the bridge, one on each side. Dynamic oscillation tests were then carried out when the trucks passed.
These dynamic and static load tests were fundamental to understand the structural reliability of the bridge, to ensure its effective operation. Structures of this type are forced to undergo dynamic stresses and very important continuous loads given the intensive use for which they were designed.

For the installation of the beams, which are 80 meters long, a crane 90 meters high and weighing 300 tons had to be positioned, capable of lifting to 600 tons of weight.

The works for the construction of the new road entrance to Val Badia with the tunnel are carried out by a business association led by Strabag. The completion of the interventions is scheduled for Christmas 2021. The new access to Val Badia includes the Floronzo tunnel, 400 meters long, continues with the 144-meter bridge over the Kniepass artificial lake which leads to a roundabout that will serve as a connection with the Val Pusteria state road (SS 49).

Dynamic and static load tests of a metal bridge on a construction site
Dynamic and static load tests of a metal bridge on a construction site
Dynamic and static load tests of a metal bridge on a construction site

Other case studies

Bridges

Bridge of the Gods: wireless structural health monitoring for a historic Columbia River crossing

Discover how Move Solutions and Parsons deployed a wireless structural health monitoring system on the Bridge of the Gods in Oregon, capturing real-time data on stress, vibration, and movement to protect and extend the life of this historic Columbia River crossing, an early but crucial step toward ensuring its safety, resilience, and preservation for decades to come.

Cascade Locks, Oregon (US)

Read case study
Buildings and heritage sites

Basilica of Saint Francis of Assisi – Structural monitoring during construction

Move Solutions deployed a structural health monitoring system to allow monitoring of vibrations and rotations in the Basilica of San Francesco during the construction of a new connecting gallery and elevator, protecting Giotto’s frescoes.

Basilica of Saint Francis of Assisi

Read case study
Bridges

Transforming bridge safety with real-time structural health monitoring in West Virginia

Wireless sensors and a real-time monitoring platform provide continuous insight into the bridge’s dynamic behavior, helping engineers assess structural performance, reduce special inspections, and support more efficient maintenance decisions.

Huntington, USA

Read case study
Bridges

Wireless Monitoring of the Zambeccari Bridge in Tuscany

The Zambeccari bridge in Pontremoli was built in the early 1900s on the Verde stream. It is a reinforced concrete bridge developed on two spans of the same length. In May 2020, the closure to both vehicular and pedestrian traffic is ordered for structural checks. The objective of the temporary closure of the structure is to clarify the state of health of the bridge and its structural degradation. After verifying the state of the Zambeccari bridge by the Vega Engineering Company, the structure was reopened with a reduced carriageway. Vega has prepared, with the approval of the municipality, the insertion of a continuous and remote structural monitoring system.

Pontremoli, Tuscany, Italy

Read case study