The Gelida Wall Collapse and Retaining Wall Monitoring on Railways
Join the Move Solutions newsletter
Stay updated on product releases, news, and upcoming webinars.
On 20 January 2026, at 21:23, a Rodalies train on the R4 line hit a fallen segment of concrete wall near Gelida, in Catalonia. A trainee traveling in the cab died. Five people were seriously injured, among them the driver and two trainee drivers, and 36 more had minor injuries.
It was the second fatal accident on the R4 caused by a wall falling onto the track in a little over seven years. In both cases investigators pointed to water behind the wall, which inspectors cannot see during a normal assessment visit. For this reason, infrastructure managers need sensors for retaining wall monitoring, which gives engineers more information about parameters that are not observable with the naked eye.
Gelida
The segment that fell on the track on 20 January was a precast L-shaped element of a wing wall. The wing wall belonged to the cut-and-cover structure that carries the AP-7 motorway over the railway. The Spanish railway accident investigation commission (CIAF) published a preliminary note. According to the note, the segment was leaning at about 45 degrees into the clearance of the track at the moment of impact. It presumably collapsed under the pressure of water accumulated behind it, after heavy rain on the day of the accident and on the days before. From the train recorder, the CIAF found that the train had about five seconds and 50 meters between the start of braking and the collision. Its working hypothesis is that the train arrived while the wall was falling.
In the next phases, the CIAF will examine the design and condition of the wall, the drainage of the earthwork at that point of the AP-7, and the previous inspections and interventions. It expects to publish the final report within a year of the accident. Adif manages the rail infrastructure. In April 2026 the president of the CIAF stated that both Adif and the road authority had inspected the structure. Two preliminary expert reports have been written. CEDEX wrote one for the Directorate General of Roads, which owns the structure. The consultancy FHECOR wrote the other for the contractor in charge of its maintenance. The two teams disagree on the origin of the corrosion found in the wall, but both concluded that the failure was hard to foresee. Other parties contest that conclusion in the court case that followed. The CIAF will say in its final report what inspectors could have seen beforehand.
Vacarisses
On 20 November 2018, so 5 years before the Gelida accident, at 06:15, a Rodalies train from Manresa hit the rocks of a masonry wall between Vacarisses and Vacarisses-Torreblanca. The wall protected the slope of a cutting, and part of it had collapsed onto the track. One person died, six were seriously injured and 46 had minor injuries. In its final report, the CIAF found that the inspections required by Adif's procedures had been carried out. They included an extra cab inspection on the day before the accident. According to the CIAF, the wall had given no sign of deterioration that would have warned of its collapse. As a contributing factor, the commission identified runoff from the adjacent C-58 road. The water overflowed a drainage grate and fell onto the railway slope and behind the wall.
There was no adverse weather on the morning of the collapse. In the previous days, Adif had received no rain alerts for that section from AEMET, the Spanish weather agency. However, on 15 November a train driver had reported a flooded track and water cascading down the cuttings at the same point. Adif's rain protocol is based on forecasts. Adif matches the sections of its network to 5 by 5 km AEMET grid cells, and it receives alerts from 20 mm of forecast rain in six hours. Higher alert levels start at 40 and 80 mm. At the listed risk points, Adif responds with inspections, speed restrictions or suspension of traffic, depending on the alert level and on the risk of the point. Among the root causes, the CIAF listed the insufficiency of this protocol, because forecasts and other weather data did not match. It recommended identifying walls with similar characteristics that are exposed to external agents, such as other infrastructure or water discharges, which could compromise their stability.
Retaining wall monitoring
According to the CIAF, water behind the wall played a part in both accidents, and inspectors cannot see that load. Water pressure in the backfill adds to the earth pressure. On a cantilever or L-shaped wall, the result is an overturning moment about the toe. The stem and its connection to the base resist that moment. Drainage can be blocked, or water can arrive from outside the catchment the wall was designed for, as from the road above at Vacarisses. In these cases the pressure rises with the rain and falls slowly afterwards, so a wall can collapse days after the rain.
Sensors can follow this mechanism continuously through two quantities. The first is the water level or pressure behind the wall, measured by standpipes or piezometers in the backfill. The second is the rotation of the wall, measured by tiltmeters fixed to the face. At the top of a cantilever stem, a rotation of 1 milliradian corresponds to 1 millimeter of horizontal movement per meter of height. Tiltmeters like the TLT-STD-LR-2 resolve rotations below a milliradian. Devices like the Communication Node (SCN-XXX-LR-2) can connect piezometers with analog output, so MyMove records rotation and water level together.
With both records, engineers can check after a rain event whether the wall rotates when the water rises and recovers when it falls. Part of the rotation can also remain. If the wall returns to its previous position, it is behaving elastically. If the residual rotation grows from one rain event to the next, the wall, its connection or its foundation is yielding. In that case the owners of both the wall and the track need an alarm. Alarms in MyMove can be set on rotation and on water level, so the infrastructure manager receives a notification when a wall moves, independently of the forecast.
The limit is a brittle failure. Corrosion can reduce the capacity of the connection between stem and base, and in that case a wall can fail with little rotation beforehand. Only inspectors examining the connection can find that kind of damage. Infrastructure managers can start from the walls described in the 2018 CIAF recommendation, which have an external source of water such as road drainage from above. They can also start from walls where the road authority owns the structure and the rail infrastructure manager owns the track below, as at Gelida, because both owners need the same data.
Frequently Asked Questions
Could a tiltmeter have warned of the Gelida collapse?
Nobody can say before the final report. Tiltmeters give warning when a wall rotates progressively before failing. The CIAF has described the wall falling as the train arrived, but not how the wall behaved in the hours or days before. If the failure started at a corroded connection with little rotation, tiltmeters would have recorded it rather than anticipated it.
Which parameters should be measured on a railway retaining wall?
Rotation of the wall face, water level or pressure in the backfill, and rainfall at the site, read together. Where cracks or open joints are present, crack meters measure how they open over time. On long walls, settlement readings at the crest show whether one section is moving relative to the next.
Why are visual inspections not enough for retaining walls exposed to water?
Because inspectors record the condition of the wall on the day of the visit. The water pressure behind it changes with the rain and leaves no visible trace until the wall moves. At Vacarisses, the inspectors had found no sign of deterioration during the inspections required by procedure.