A construction site next to a tunnel can deform it, settle it and make it vibrate, so engineers measure these effects in the tunnel before, during and after the works.

In Newcastle upon Tyne, the Pilgrim's Quarter development was built next to the underground Metro tunnels. Nexus owns the tunnels and operates the trains. It required monitoring of the tunnels for the two years of works and for one more year after completion.

A construction site can deform a nearby tunnel and make it vibrate. For this reason, engineers design the structural monitoring for tunnels next to a construction site around the expected effects of the works.

What a construction site does to a tunnel

A construction site can affect a nearby tunnel in three ways. Excavation removes soil next to or above the tunnel, so the ground around the lining unloads and the tunnel can heave or deform. New foundations add load to the ground, and the ground under them settles. This settlement can continue after the end of the works, because the soil takes time to consolidate under the new load. Piling, demolition and excavation also make the tunnel vibrate.

The size of these effects depends on the distance from the tunnel, on the ground and on the type of works. For this reason, engineers have to measure them in the tunnel.

What to measure in the tunnel

Engineers have to measure two different things in the tunnel. The first is deformation, that is the movement of the lining and the change in shape of the cross-section. The second is the vibration that reaches the tunnel from the site.

For deformation, the usual instruments are an automated total station with prisms on the lining, or tiltmeters fixed to the lining. A total station gives the position of the prisms in three dimensions, but it needs a clear line of sight along the tunnel. A tiltmeter gives the rotation of the lining at the point where it is fixed, and it needs no line of sight. Tiltmeters like the TLT-STD-LR-2 measure rotation with sub-milliradian resolution, so engineers can use them in short or curved tunnels, shafts and ventilation galleries.

The project in Newcastle had both of these situations. In the running tunnel, 155 meters needed monitoring, and Academy Geomatics installed an automated total station. It divided the tunnel into eighteen sections that matched the locations of the adjacent piles. In all eighteen sections, five prisms around the lining showed whether one side of the tunnel moved more than the other. The ventilation tunnel is 28 meters long and it offered no line of sight for a total station. For this reason, Academy Geomatics divided it into three cross-sections with three tiltmeters per section.

For vibration, vibrometers measure peak particle velocity (PPV). Construction vibration limits, such as those in BS 7385, are based on PPV. Accelerometers measure the dynamic response of the structure. The Modal Analysis Tool in MyMove includes frequency domain decomposition (FDD), and with it engineers can extract the natural frequencies of the tunnel from the accelerometer records. If the frequencies shift between readings taken under comparable conditions, the stiffness of the structure has changed. In Newcastle, Academy Geomatics installed accelerometers at both ends of the ventilation tunnel and two more in the running tunnel. It also installed one vibrometer per tunnel.

Where to install and for how long

Engineers place the sensors according to the position of the works. When the monitored sections match the piles, as in Newcastle, engineers can compare the readings of a section with the work on the nearest pile.

Access to the tunnel is the second constraint. In a running metro tunnel, installers can usually work only in the night hours without service. In Newcastle, the installation of the whole system took a week of night shifts in July 2022. Wireless sensors have their own battery and radio, so the installers do not need to run cables along the tunnel or across the track.

Underground, the radio link needs planning. LoRa signals attenuate quickly near the entrance of a tunnel. Deeper inside, they travel longer distances because the tunnel works like a lossy waveguide. For this reason engineers place gateways and repeaters at portals and shafts, as described in the guide to LoRaWAN repeater placement in complex terrain.

Engineers start the monitoring before the works. They use the readings taken before the works as a baseline, so they can separate the effect of the works from the normal movement of the tunnel. They also continue the monitoring after the works, because the settlement under new foundations can continue. In Newcastle, Nexus required one more year after completion, and a full year also includes a complete seasonal cycle of temperature. Alarms in MyMove can be set on the thresholds agreed with the tunnel owner, so the contractor and the owner receive a notification when the readings cross them.

Other articles

Subscribe to Updates

Stay informed about our latest innovations and insights.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.


Registered office

Piazza Cavour, 7, 20121 Milan – Italy

Corporate offices

Via Marcantonio Colonna, 35, 20149 Milan – Italy
Via Carlo Piaggia, 382, 55100 Lucca – Italy
111 W Main St, Mt Pleasant, Pennsylvania – USA

Copyright © 2025 Move S.p.A. All rights reserved – VAT NUMBER: 09887990969 – Registered capital: 500.000€ i.v